» Workers’ Compensation Coverage according to Statute of the State of New
Hampshire:
$100,000 / $500,000 / $100,000
The City of Nashua must be named as an additional insured on all liability certificates.
All bidders and subcontractors at every tier under the bidder will fully comply with NH RSA Chapter 281-
A,
‘Workers’ Compensation”. It is the responsibility of the CONTRACTOR to submit to the OWNER
certificates of insurance for the Designer and all other subcontractors prior to the start of the project. It
is the responsibility of the CONTRACTOR to provide the OWNER with updated certificates of insurance
for the CONTRACTOR and all subcontractors 10 days prior to the expiration of coverage. The OWNER
may, at any time, order the CONTRACTOR to stop work, suspend the contract or terminate the contract
for non-compliance. All subcontractors except for Designer are subject to the same insurance
requirements as the CONTRACTOR,
The successful bidder will be required to post a 100% Performance Bond and a 100% Payment Bond in
an amount equal to the Contract Award.
Pursuant to NRO 5-71 (A), the City of Nashua supports the concept of purchasing products which are
biodegradable, can be or have been recycled, or are environmentally sounds. Due consideration will be
given to the purchase of such products. If you are bidding on any such products which qualify, please so
indicate in a cover sheet by item number and description.
The City is exempt of all taxes. All bids must be FOB Nashua, NH. All bidders must comply with all
applicable Equal Employment Opportunity laws and regulations.
Pursuant to NRO 5-78 (F), the purchasing manager shall not solicit a bid from a contractor who is in
default on the payment of taxes, licenses or other monies due the city. Therefore, this bid request is
void as to anyone who is in default on said payments.
Respectfully,
4 op
i Pir —
an Kooken
Purchasing Manager
City of Nashua
KookenD@nashuanh.gov
RFPO609-031116 LED Street Lighting Conversion Project