  2. Board Of Aldermen - Minutes - 5/24/2016 - P19

Board Of Aldermen - Minutes - 5/24/2016 - P19

By dnadmin on Sun, 11/06/2022 - 21:35
Document Date
Tue, 05/24/2016 - 00:00
Meeting Description
Board Of Aldermen
Document Type
Minutes
Meeting Date
Tue, 05/24/2016 - 00:00
Page Number
19
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/boa_m__052420…

City of Nashua

Public Works Division
9 Riverside Street
Nashua, NH 03062

Engineering Department

9 Riverside Street
Fax (603) 589-3169

Date:

To:

From:

Ce:

Re:

MEMO

May 23, 2016
Brian S. McCarthy, President of Board of Aldermen

Stephen Dookran, P.E., City Engineer
Sonia Shahnaj, P.E., Senior Staff Engineer

Mayor Jim Donchess
Lisa Fauteux, Director of Public Works

(R-16-038) Authorizing the Mayor to enter into an Amendment to the Railroad Agreement with
the State of New Hampshire and Pan Am Railways for the purpose of replacing a railway

highway crossing on East Hollis Street

- Request for the first and second reading at the May 24, 2016 meeting

The original three-way Agreement was executed in August 2015, but the work did not proceed essentially due to
financial hurdles involving the Railroad as they were unable to allocate funding to purchase materials needed for the
project. Since NHDOT does not have a policy of paying upfront, the Railroad and the NHDOT requested the City to
bear the upfront cost of the materials approximately in the amount of $130,000.00. The City will be fully reimbursed
by NHDOT for this cost after the project is complete. The timing is critical for the following reasons:

1. According to the NHDOT, who is administering the Federal funds, if the project is not completed in the 2016
Federal funding year which ends in September 2016, the funding will no longer be available for this project. In
order to complete this project by September 2016, the construction must begin no later than middle of July

2016.

2. The project is about 95% funded by FHWA and the remaining 5% is City’s share. Should the resolution be
referred to committees for recommendations, the current schedule for aldermanic meetings will put final
approval too late for the project and the City will be in jeopardy of losing Federal funding in the amount of
$606,299.87.

3. The City must make payment to the Railroad without delay for the Railroad to order the materials with long-
lead time to start construction by the July 2016 deadline.

The crossing on East Hollis Street has been in a deteriorated condition for many years and interim repairs have not
held up. This project will not only include the needed repairs but also upgrading the crossing to meet Federal railroad
safety standards. In addition to the improvements associated with railroad crossing, the project includes improvements
to curbing, sidewalk, new pavement and striping at the intersection.

Administration
Business Office
(603) 589-3140

Street/Traffic City Parks-Recreation
Department Engineer Department
(603) 589-4750 (603) 589-3120 (603) 589-3370

Solid Waste
Department
(603) 589-3410

Wastewater
Treatment Plant
(603) 589-3560

Page Image
Board Of Aldermen - Minutes - 5/24/2016 - P19

Footer menu

  • Contact