CHANGE ORDER
No. 1
PROJECT: Nashua Transit Center Retrofit
OWNER'S CONTRACT NO.: __ REPO979-040821
EXECUTED CONTRACT DATE: July 15, 2021
DATE OF ISSUANCE: _ September 9, 2021. EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 165194
CONTRACTOR: DL King & Associates, Inc.
ENGINEER: Greenman-Pedersen, Inc.
The Contract is modified as follows upon execution of this Change Order:
Description:
Roadway work area expanded by approximately two feet within the City of Nashua right-of-way along the
frontage of PRG. Work items are estimated according to the current bid prices at the existing contract
specified requirements. For payment, these items will be measured and paid according to the existing
contract terms, measured-in-place.
Justification:
Nashua DPW sewer main work within the limits of City Hall Way caused water service damage to the PRG
water service connection. To repair correctly, the drive apron along PRG frontage on City right of way is in
need of repair.
Attachments:
e [tems List
e = =Plan View of Adjusted Work Area
Change Order #1 1 of 2