CHANGE ORDER
SUMMARY
CHANGE IN CONTRACT PRICE
Original Contract Price:
$ 1,129,710.00
CHANGE IN CONTRACT TIMES
Original Contract Times:
Substantial Completion: October 17, 2021
Ready for Final Payment: November 16, 2021
Net Changes from previously approved Change Orders
§ 5,611.84
Net Changes from previously approved Change Orders
Substantial Completion: 7
Ready for Final Payment: 7
Contract Price prior to this Change Order:
$ 1,135,321.84
Contract Times prior to this Change Order:
Substantial Completion: October 24, 2021
Ready for Final Payment: November 23, 2021
Increase (Decrease) of this Change Order:
$11,905.95
increase (Decrease) of this Change Order:
Substantial Completion: 29 Calendar Days
Ready for Final Payment: 22 Calendar Days
Contract Price with all approved Change Orders:
S 1,147,227.79
Contract Times with all approved Change Orders:
Substantial Completion: December 15, 2021
Ready for Final Payment: December 15, 2021
RECOMMENDED BY: ACC
By: Toe Lovie By:
D BY: ACCEPTED BY:
By:
Engineer (Authorized Signature}
Greenman-Pedersen, Inc.
Lo re
Contractor frathortzed Signature}
dD. he Minn
Owner (Authorized Signature)
Director of Construction Eng. __
Title: Title:
(CE © ¥ Title:
Date: 11/2/2021
Change Order #2 3 of 3
Date: LL, Bf Date: