parcels or groups of parcels, where forest management plans will be beneficial. This task will be
completed no later than January 31, 2022.
Phase 3: Review First Draft
After the Commissioners have reviewed the first draft of the updated document. NRPC will reserve three
hours to discuss the document with Commissioners and take their feedback. This review will include two
hours to be set aside to attend the Commission meeting on February 1, 2022. An additional hour will be
reserved to receive feedback from Commissioners by video conference, phone, or email. NRPC will accept
feedback on the first draft through February 28, 2022.
Phase 4: Second Draft
After considering and incorporating all feedback provided by Commissioners, NRPC will revise the
document and create a second draft. The second draft will have the look and feel of a final document, and
it will be again submitted to the Commission for review. This task will occur no later than March 31, 2022.
Phase 5: Review Second Draft
After the Commissioners reviewed the second draft of the updated document. NRPC will reserve four
hours to discuss the document with Commissioners and take their feedback. This review will include two
hours to be set aside to attend the Commission meeting on April 5, 2022. Two additional hours will be
reserved to receive feedback from Commissioners by video conference, phone, or email. NRPC will accept
feedback on the second draft through April 31, 2022.
Phase 6: Final Report
After considering and incorporating all feedback provided by Commissioners, NRPC will revise the
document and create a final, updated version of The City of Nashua Natural Resource Inventory and
Conservation Plan. The final document will be submitted to the Commission no later than June 30, 2022.
Project Timeline:
Task sro/ur Amount Est. Completion
1 Map Update (18) 25 $1,750 December 31, 2021
2 First Draft 20 $1,400 January 31, 2022
3 Review First Draft 3 $210 February 28, 2022
4 Second Draft 20 $1,400 March 31, 2022
5 Review Second Draft 4 $280 May 31, 2022
6 Final Draft 18 $1,260 June 30, 2022
NRPC Task Order: Nashua Conservation Commission NRI Update
2