Requests for payment shall be submitted no later than fifteen (15) days after the end of each month and
must include a detailed summary of the expenditures reported in a form that supports the approved budget.
Specifically, Professional Engineer agrees to provide the following with each request for payment:
1. Appropriate invoice forms. The forms shall include the project purchase order number, a listing
of personnel hours and billing rates, and other expenditures for which payment is sought.
2. A progress report. The report shall include, for each monthly reporting period, a description of
the work accomplished, problems experienced, upcoming work, any extra work carried out, and a
schedule showing actual expenditures billed for the period, cumulative total expenditures billed and
paid to date under the contract, and a comparison of cumulative total expenditures billed and paid
to the approved budget.
The City of Nashua will pay for work satisfactorily completed by Professional Engineer. The City of Nashua
will pay Professional Engineer within 30 days of approval by the City of Nashua of the submitted invoice
forms and progress reports. The City of Nashua will make no payments until the invoice forms and progress
reports have been submitted and approved.
5. Effective Date of Contract. This contract shall not become effective until and unless approved by the City
of Nashua.
6. Notices. All notices, requests, or approvals required or permitted to be given under this contract shall
be in writing, shall be sent by hand delivery, overnight carrier, or by United States mail, postage prepaid,
and registered or certified, and shall be addressed to:
CITY OF NASHUA REPRESENTATIVE: HAYNER/SWANSON REPRESENTATIVE:
Daniel Hudson, P.E. — City Engineer John Vancor, P.E. — Vice President
Division of Public Works, Engineering Hayner/Swanson, Inc.
9 Riverside Street 3 Congress Street
Nashua, NH 03062 Nashua, NH 03062
Any notice required or permitted under this contract, if sent by United States mail, shall be deemed to be
given to and received by the addressee thereof on the third business day after being deposited in the mail.
The City of Nashua or Professional Engineer may change the address or representative by giving written
notice to the other party.
AG 3 of 4