CHANGE ORDER
SUMMARY
CHANGE IN CONTRACT PRICE
Original Contract Price:
S$ 1,129,710.00
CHANGE IN CONTRACT TIMES
Original Contract Times:
Substantial Completion: October 17, 2021
Ready for Final Payment: November 16, 2021
Net Changes from previously approved Change Orders
$ 17,517.79
Net Changes from previously approved Change Orders
Substantial Completion: 36
Ready for Final Payment: 29
Contract Price prior to this Change Order:
$ 1,147,227.79
Contract Times prior to this Change Order:
Substantial Completion: December 15, 2021
Ready for Final Payment: December 15, 2021
Increase (Decrease) of this Change Order:
S$ 38,248.61
Increase (Decrease) of this Change Order:
Substantial Completion Internal Work: February 15, 2022
Substantial Completion External Work: May 15, 2022
Ready for Final Completion: May 31, 2022
Contract Price with all approved Change Orders:
$ 1,185,476.40
Contract Times with all approved Change Orders:
Substantial Completion Internal Work: February 15, 2022
Substantial Completion External Work: May 15, 2022
Ready for Final Completion: May 31, 2022
RECOMMENDED BY:
ACCEPTED BY:
ACCEPTED BY:
By: By: By:
Engineer (Authorized Signature) Contractor (Authorized Signature) Owner (Authorized Signature)
Greenman-Pedersen, Inc.
Director of Construction Eng.
Title: Title: Title:
Date: Date: Date:
Change Order #3 4 of 4