Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 12/15/2021 - P16

Finance Committee - Agenda - 12/15/2021 - P16

By dnadmin on Mon, 11/07/2022 - 13:50
Document Date
Fri, 12/10/2021 - 16:30
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 12/15/2021 - 00:00
Page Number
16
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__121520…

CHANGE ORDER

PROJECT: Nashua Transit Center Retrofit

OWNER'S CONTRACT NO.: __ RFP0979-040821

EXECUTED CONTRACT DATE: July 19, 2021

DATE OF ISSUANCE: _December 3, 2021 EFFECTIVE DATE: Upon City Approval

OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 165194
CONTRACTOR: DL King & Associates, Inc.
ENGINEER: Greenman-Pedersen, Inc.

The Contract is modified as follows upon execution of this Change Order:

Description/Justification:

COR 4: Window Credit

During construction it was discovered that an unknown exterior column with diagonal straps exist within the
exterior walls where a window was to be installed. With the combination of these two features, there is no
room to add a window without major structural work to the building. It was determined that seeking a credit
for the window work was more cost effective than adding structural design and work to the building exterior
walls.

COR 5: Water Meter Closet

During a permit review by Pennichuck Water, it was requested that the water meter location be revised to
provide for a larger space for the water meter to reside. The only acceptable location for this is a new closet in
the entry way. This work includes some demolition, new wall framing, new door, water fountain changes and
closet shelves.

COR 7: Entry Doors

The contract was asked to submit a proposal to provide new entry doors for both the main entrance on the
north side of the transit center as well as the west side of the center. Four exterior doors total were proposed
and priced to the City. With major construction activities underway, it was determined that the existing doors
do not have much service life remaining and there is already a contractor mobilized performing renovation
work.

Change Order #3 1 of 4