SUBJECT: Change Order to Transit Center Renovation in the amount not to exceed $55,766.40
funded from 54300 Sewer Maintenance/Wastewater Fund ($5,611.84) 81200 Buildings &
Improvements/ FTA Grant Funds ($50,154.56)
The City has previously entered into a contract as follows:
Vendor: DL King
Original contract approval amount: $1,129,710.00
Date originally sent to Finance: May 19, 2021
Total value including all change orders previously presented: $1,147,227.79
Total new value including change orders being presented today: $1,185,476.40
Please see attached communications from Camille Correa, Transportation Manager, dated December 15,
2021 for project specific details related to these Change Orders:
CO# Change Detail Communicated | Change Value
to Finance
1 Roadwork repair needed for underground sewer line repair 12/1/21 $5,611.84
(to be paid out of Wastewater fund)
2 Tile & grout changes, drainage grade and pipe changes to a 12/1/21 $11,905.95
manhole & catch basin due to gas utility pipe elevations
3 Interior Changes $38,248.61
Change Order Total $55,766.40
The Community Development Division: Transit Department, and the Purchasing Department respectfully
request your approval of these changes.
Regards,
Kelly Parkinson