Finance Committee - Agenda - 11/17/2021 - P118

By dnadmin on Mon, 11/07/2022 - 13:50
Document Date
Wed, 11/10/2021 - 18:08
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 11/17/2021 - 00:00
Page Number
118
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__111720…

Init.

§ 5.2.2 The Guaranteed Maximum Price is subject to additions and deductions by Change Order as provided in the
Contract Documents and the Date of Substantial Completion shall be subject to adjustment as provided in the
Contract Documents.

§ 5.3 Changes in the Work

§ 5.3.1 The Owner may, without invalidating the Contract, order changes in the Work within the general scope of the
Contract consisting of additions, deletions or other revisions. The Owner shall issue such changes in writing. The
Architect may make minor changes in the Work as provided in Section 7.4 of ALA Document A201-2007, General
Conditions of the Contract for Construction. The Construction Manager shall be entitled to an equitable adjustment
in the Contract Time as a result of changes in the Work.

§ 5.3.2 Adjustments to the Guaranteed Maximum Price on account of changes in the Work subsequent to the
execution of the Guaranteed Maximum Price Amendment may be determined by any of the methods listed in
Section 7.3.3 of AIA Document A201-2007, General Conditions of the Contract for Construction.

§ 5.3.3 In calculating adjustments to subcontracts (except those awarded with the Owner’s prior consent on the basis
of cost plus a fee), the terms “cost” and “fee” as used in Section 7.3.3.3 of ALA Document A201~-2007 and the term
“costs” as used in Section 7.3.7 of AIA Document A201-2007 shall have the meanings assigned to them in AIA
Document A201-2007 and shall not be modified by Sections 5.1 and 5.2, Sections 6.1 through 6.7, and Section 6.8
of this Agreement. Adjustments to subcontracts awarded with the Owner’s prior consent on the basis of cost plus a
fee shall be calculated in accordance with the terms of those subcontracts.

§ 5.3.4 In calculating adjustments to the Guaranteed Maximum Price, the terms “cost” and “costs” as used in the
above-referenced provisions of ALA Document A201—2007 shall mean the Cost of the Work as defined in Sections
6.1 to 6.7 of this Agreement and the term “fee” shall mean the Construction Manager’s Fee as defined in Section 5.1
of this Agreement.

§ 5.3.5 If no specific provision is made in Section 5.1.2 for adjustment of the Construction Manager’s Fee in the case
of changes in the Work, or if the extent of such changes is such, in the aggregate, that application of the adjustment
provisions of Section 5.1.2 will cause substantial inequity to the Owner or Construction Manager, the Construction
Manager’s Fee shall be equitably adjusted on the same basis that was used to establish the Fee for the original Work,
and the Guaranteed Maximum Price shall be adjusted accordingly.

ARTICLE 6 COST OF THE WORK FOR CONSTRUCTION PHASE

§ 6.1 Costs to Be Reimbursed

§ 6.1.1 The term Cost of the Work shall mean costs necessarily incurred by the Construction Manager in the proper
performance of the Work. Such costs shall be at rates not higher than the standard paid at the place of the Project
except with prior consent of the Owner. The Cost of the Work shall include only the items set forth in Sections 6.1
through 6.7.

§ 6.1.2 Where any cost is subject to the Owner’s prior approval, the Construction Manager shall obtain this approval
prior to incurring the cost. The parties shall endeavor to identify any such costs prior to executing Guaranteed
Maximum Price Amendment.

§ 6.2 Labor Costs
§ 6.2.1 Wages of construction workers directly employed by the Construction Manager to perform the construction
of the Work at the site or, with the Owner’s prior approval, at off-site workshops.

§ 6.2.2 Wages or salaries of the Construction Manager’s supervisory and administrative personnel when stationed at
the site with the Owner’s prior approval.

(If it is intended that the wages or salaries of certain personnel stationed at the Construction Manager's principal
or other offices shall be included in the Cost of the Work, identify in Section 11.5, the personnel to be included,
whether for all or only part of their time, and the rates at which their time will be charged to the Work.)

§ 6.2.3 Wages and salaries of the Construction Manager’s supervisory or administrative personnel engaged at
factories, workshops or on the road, in expediting the production or transportation of materials or equipment
required for the Work, but only for that portion of their time required for the Work.

AIA Document A133” — 2009 (formerly A124™CMc ~ 2003). Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.

The “Amencan Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission 40
This document was produced by AIA software at 11:15:33 ET on 05/04/2021 under Order No.4797552925 which expires on 09/23/2021, is not for resale, is

licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail
copyright@aia.org.

User Notes: (3B9ADA4E)