CO #2 Added Smoke-Heat Detectors $2,322.54
CO #2 Change Tax Office Entrance ($4,963.20)
CO #2 Firestop Assessing Firewall $4,443.32
CO #2 Install Pipe Insulation in Assessing $2,925.46
CO #2 Drywall Changes in Assessing $4,229.60
CO #2 Access Control Changes _ $2,580.60
Total CO #2: $11,538.32
Justification:
All of the above changes were as of a result of unforeseen structural items discovered
during construction.
CO #3 Skim Coat Assessing Area Walls $4,840.27
CO #3 Rooftop Equipment Rails _ $4,220.03
Total CO #3: $9,060.30
Justification:
All of the above changes were as of a result of unforeseen structural items discovered
during construction.
The total of the project as of December 28, 2020 is $939,895.45