Hampshire) Superior Court Southern Judicial District or in the New Hampshire 9th Circuit
Court—Nashua and not elsewhere
ARTICLE 19 — MISCELLANEOUS PROVISIONS
1. Neither party to the Contract shall assign the Contract as a whole without written consent
of the other.
2. Tests, inspections and approvals of portions of the Work required by the Contract
Documents or by laws, ordinances, rules, regulations or orders of public authorities having
jurisdiction shall be made at an appropriate time.
If additional testing is required, the CONTRACTOR shall perform these tests.
4. The OWNER shall pay for tests except for testing Work found to be defective for which
the CONTRACTOR shall pay.
wo
IN WITNESS WHEREOF, the parties hereto have caused this contract to be signed and intend to be
legally bound thereby.
City of Nashua, NH (signature) CONTRACTOR (signature)
James W.Donchess, Mayor
(Printed Name and Title) (Printed Name and Title)
Date Date
CA- 12 of 12