Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 2/17/2021 - P216

Finance Committee - Agenda - 2/17/2021 - P216

By dnadmin on Mon, 11/07/2022 - 13:48
Document Date
Fri, 02/12/2021 - 11:32
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 02/17/2021 - 00:00
Page Number
216
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__021720…

3.

Change Order requests must include material and equipment cost plus labor with a profit
margin of no more than 10%. Change Orders may require approval by the Board of
Public Works and the OWNER’s Finance Committee vote prior to proceeding.

The OWNER will have authority to order minor changes in the Work not involving
changes in the Contract Sum or the Contract Time and not inconsistent with the intent of
the Contract Documents. Such changes shall be written orders and shall be binding on the
OWNER and CONTRACTOR. The CONTRACTOR shall carry out such written orders
promptly.

If concealed or unknown physical conditions are encountered at the site that differ
materially from those indicated in the Contract Documents or from those conditions
ordinarily found to exist, the Contract Sum and Contract Time shall be subject to equitable
adjustment following authorization of the OWNER to the charges.

ARTICLE 10 — TIME

1.
2.

Time limits stated in the Contract Documents are of the essence to the Contract.

If the CONTRACTOR is delayed at any time in progress of the Work by changes ordered
in the Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties
or other causes beyond the CONTRACTOR’s control, the Contract Time shall be
extended by Change Order for such reasonable time as may be determined.

ARTICLE 11 —- PAYMENTS AND COMPLETION

1.

The Contract Sum stated in the Agreement, including authorized adjustments, is the total
amount payable by the OWNER to the CONTRACTOR for performance of the Work
under the Contract Documents.

Once every thirty (30) days, the CONTRACTOR shall submit an itemized Application
for Payment for operations completed in accordance with the values stated in the
Agreement. Such application shall be supported by such data substantiating the
CONTRACTOR’s right to payment as the OWNER may reasonably require.

Application for Payment performed under this agreement shall be submitted as follows:

>» Electronically via email to VendorAPInvoices@NashuaNH. gov

OR

>» Paper Copies via US Mail to:
City of Nashua, City Hall
Accounts Payable
229 Main Street
Nashua, NH 03060

Please do not submit invoices both electronically and paper copy.

In addition, and to facilitate the proper and timely payment of applications, the
OWNER requires that all submitted invoices contain a valid PURCHASE ORDER
NUMBER.

The CONTRACTOR warrants that title to all Work covered by an Application for
Payment will pass to the OWNER no later than the time of payment. The
CONTRACTOR further warrants that upon submittal of an Application for Payment, all

CA- 7 of 12