CERTIFICATE OF SUBSTANTIAL COMPLETION
PROJECT: Dry Well Hoist Replacement
OWNER’S CONTRACT NO: IFB1093-122920
DATE OF ISSUANCE:
OWNER: City of Nashua, NH
OWNER’ s Purchase Order NO.:
CONTRACTOR: Mass Crane and Hoist Service
The Work to which this Certificate applies has been inspected by authorized representative of OWNER,
CONTRACTOR, and ENGINEER, and that Work is hereby declared to be substantially complete in
accordance with the Contract Documents on
(DATE OF SUBSTANTIAL COMPLETION)
A Tentative list of items to be completed or corrected is attached hereto. This list may not be all-
inclusive, and the failure to include an item in it does not alter the responsibility of CONTRACTOR to
complete all the Work in accordance with the Contract Documents. The items in the tentative list shall
be completed or corrected by CONTRACTOR within days of the above date of
Substantial Completion.
This certificate does not constitute an acceptance of Work not in accordance with the Contract
Documents nor is it a release of CONTRACTOR’s obligation to complete the Work in accordance with
the Contract Documents.
EXECUTED BY DPW ENGINEER: ACCEPTS THIS CERTIFICATE OF SUBSTANTIAL ACCEPTS THIS CERTIFICATE OF SUBSTANTIAL
COMPLETION: COMPLETION:
By: By: By:
(Authorized signature) Owner Representative Contractor (Authorized Signature)
Title: Title: Title:
Date: Date: Date: