In addition, and to facilitate the proper and timely payment of applications, the City of Nashua
requires that all submitted invoices contain a valid PURCHASE ORDER NUMBER.
Requests for payment shall be submitted no later than fifteen (15) days after the end of each
month and must include a detailed summary of the expenditures reported in a form that supports
the approved budget. Specifically, Professional Engineer agrees to provide the following with
each request for payment:
1. Appropriate invoice forms. The forms shall include the project purchase order number,
a listing of personnel hours and billing rates, and other expenditures for which payment is
sought.
2. A progress report. The report shall include, for each monthly reporting period, a
description of the work accomplished, problems experienced, upcoming work, any extra
work carried out, and a schedule showing actual expenditures billed for the period,
cumulative total expenditures billed and paid to date under the contract, and a comparison
of cumulative total expenditures billed and paid to the approved budget.
The City of Nashua will pay for work satisfactorily completed by Professional Engineer. The
City of Nashua will pay Professional Engineer within 30 days of approval by the City of Nashua
of the submitted invoice forms and progress reports. The City of Nashua will make no payments
until the invoice forms and progress reports have been submitted and approved.
5. EFFECTIVE DATE OF CONTRACT. This contract shall not become effective until and unless
approved by the City of Nashua.
6. NOTICES. All notices, requests, or approvals required or permitted to be given under this
contract shall be in writing, shall be sent by hand delivery, overnight carrier, or by United States
mail, postage prepaid, and registered or certified, and shall be addressed to:
CITY OF NASHUA REPRESENTATIVE: PROFESSIONAL ENGINEER REPRESENTATIVE:
Amy Prouty-Gill Saya Ann Qualls-Hickey, PE, ENV SP
Sr. Staff Engineer Associate Vice President
City of Nashua — Div. of Public Works Hazen and Sawyer
9 Riverside Street 545 Mainstream Drive, - Suite 320
Nashua, NH 03062 Nashville, TN 37228
Any notice required or permitted under this contract, if sent by United States mail, shall be
deemed to be given to and received by the addressee thereof on the third business day after being
deposited in the mail. The City of Nashua or Professional Engineer may change the address or
representative by giving written notice to the other party.
AG 3 of 4