Application for Payment performed under this agreement shall be submitted as follows:
>» Electronically via email to VendorAPInvoices@NashuaNH. gov
OR
>» Paper Copies via US Mail to:
City of Nashua, City Hall
Accounts Payable
229 Main Street
Nashua, NH 03060
Please do not submit invoices both electronically and paper copy.
In addition, and to facilitate the proper and timely payment of applications, the OWNER
requires that all submitted invoices contain a valid PURCHASE ORDER NUMBER.
The CONTRACTOR warrants that title to all Work covered by an Application for Payment
will pass to the OWNER no later than the time of payment. The CONTRACTOR further
warrants that upon submittal of an Application for Payment, all Work for which Certificates
for Payment have been previously issued and payments received from the OWNER shall, to
the best of the CONTRACTOR’s knowledge, information and belief, be free and clear of
liens, claims, security interests or other encumbrances adverse to the OWNER’s interests.
OWNER shall make payments, for work satisfactorily completed and accurately invoiced,
on the basis of CONTRACTORSs Application for Payment, within 30 days of approval by
the OWNER.
The CONTRACTOR shall promptly pay each subcontractor and supplier out of the amount
paid to the CONTRACTOR on account of such entities’ portion of the Work.
The OWNER shall have no responsibility for the payment of money to a subcontractor or
supplier.
An Application for Payment, a progress payment, or partial or entire use or occupancy of the
project by the OWNER shall not constitute acceptance of Work not in accordance with the
requirements of the Contract Documents.
Substantial completion is the stage in the progress of the Work when the Work or designated
portion thereof is sufficiently complete in accordance with the Contract Documents so the
OWNER can occupy or utilize the Work for its intended use.
When the Work or designated portion thereof is substantially complete, the
CONTRACTOR and OWNER shall establish responsibilities for completion and shall fix
the time within which the CONTRACTOR shall finish all items on the list accompanying
the Certificate. Warranties required by the Contract Documents shall commence on the date
of Substantial Completion of the Work or designated portion thereof unless otherwise
provided in the Certificate of Substantial Completion.
Upon receipt of a final Application for Payment, the OWNER will inspect the Work. When
he finds the Work acceptable and the Contract fully performed, the OWNER will promptly
issue a final Certificate for Payment.
Acceptance of final payment by the CONTRACTOR, a subcontractor or supplier shall
constitute a waiver of claims by that payee except those previously made in writing and
identified by that payee as unsettled at the time of final Application for Payment.