NOTICE TO PROCEED
DATED:
CONTRACTOR: Stearns, Conrad, and Schmidt ADDRESS: 1260 Roger Bacon Dr., Suite 401
Engineers, Inc. dba SCS Field Services Reston, VA 20190
OWNER: City of Nashua, New Hampshire ADDRESS: 229 Main Street
Nashua, NH 03060
PROJECT: 2021 Landfill Gas Expansion
TO CONTRACTOR:
You are notified that the Contract Times under the above contract will commence to run on
,2021. By that date, you are to start performing your obligations under the
Contract Documents. In accordance with Article 3 of the Agreement, the date of Substantial
Completion is 60 calendar days from the date of issuance of the Notice to Proceed and the date
of Final Completion 90 calendar days from the date of issuance of the Notice to Proceed
Before starting any Work at the Site, Contractor must comply with the following:
Owner: City of Nashua, New Hampshire
(Owner Representative Signature)
By:
Title:
2021 Landfill Gas Expansion NOTICE TO PROCEED
Page 1 of 2