SECTION 01330
SUBMITTALS
PART 1 - GENERAL
1.1
1.2
1.3
DESCRIPTION
A.
This section specifies the general requirements and procedures for preparing
and transmitting data to ENGINEER for their information or review.
CONTRACTOR shall deliver all submittals to ENGINEER in a form acceptable to
ENGINEER.
CONTRACTOR'S DRAWINGS
A.
D.
The Drawings shall show the general arrangement and details as necessary to
provide a comprehensive description of the work to be performed.
As indicated below, CONTRACTOR shall prepare shop and working drawings,
for temporary and permanent work, and for the proposed methods of
construction as required under the applicable sections of the Specifications,
complete with all relevant calculations, descriptions, technical, and
performance data, as necessary to adequately perform the Work.
CONTRACTOR shall take responsibility for such drawings and for the safe and
successful construction of the Work.
Shop drawings shall be presented in a clear and thorough manner, complete
with respect to dimensions, design criteria, materials of construction,
manufacturer, and like information to enable ENGINEER to review information
as required.
Sheet size: 8% inches x 11 inches or larger, as required.
CONSTRUCTION PROGRESS SCHEDULES
A.
CONTRACTOR shall submit progress schedules in a format that displays the
timeframes for each Work item using individual horizontal bars. The schedule
shall include a separate bar for each major operation, identifying the first and
last workday of each operation. The schedule shall show the complete
sequence of construction activities, identify the Work of separate stages, the
projected percentage of completion for each item of Work at the time of each
Application for Payment, submittal dates for shop drawings, product data, and
samples, and product delivery dates, including those furnished by OWNER (if
any).
CONTRACTOR shall update the construction progress schedule every two
weeks during the project to reflect the Work completed and any changes in the
schedule.