  2. Finance Committee - Agenda - 3/17/2021 - P493

Finance Committee - Agenda - 3/17/2021 - P493

By dnadmin on Mon, 11/07/2022 - 13:46
Document Date
Fri, 03/12/2021 - 12:03
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/17/2021 - 00:00
Page Number
493
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__031720…

14. The CONTRACTOR shall be responsible for cutting, fitting or patching required

completing the Work or to make its parts fit together properly.

15. The CONTRACTOR shall keep the premises and surrounding area free from accumulation

of debris and trash related to the Work.

16. Upon completion of WORK, CONTRACTOR warrants and guarantees to OWNER, for

one (1) year, and that all WORK was completed in accordance with the Contract Documents
and will not be defective. CONTRACTOR’s warranty and guarantee hereunder excludes
defects or damage caused by:

> Abuse, modification, or improper maintenance or operation by persons other than
CONTRACTOR, subcontractors, suppliers, or any other individual or entity for
whom CONTRACTOR is responsible; or

> Normal wear and tear under normal usage.

ARTICLE 9 — CHANGES IN THE WORK

1.

After execution of the Contract, changes in the Work may be accomplished by Change Order
or by order for a minor change in the Work. The OWNER, without invalidating the
Contract, may order changes in the Work within the general scope of the Contract consisting
of additions, deletions or other revisions, the Contract Sum and Contract Time being adjusted
accordingly.

A Change Order shall be a written order to the CONTRACTOR signed by the OWNER to
change the Work, Contract Sum or Contract Time.

Change Order requests must include material and equipment cost plus labor with a profit
margin of no more than 10%. Change Orders may require approval by the Board of Public
Works and the OWNER’s Finance Committee vote prior to proceeding.

The OWNER will have authority to order minor changes in the Work not involving changes
in the Contract Sum or the Contract Time and not inconsistent with the intent of the Contract
Documents. Such changes shall be written orders and shall be binding on the OWNER and
CONTRACTOR. The CONTRACTOR shall carry out such written orders promptly.

If concealed or unknown physical conditions are encountered at the site that differ materially
from those indicated in the Contract Documents or from those conditions ordinarily found to
exist, the Contract Sum and Contract Time shall be subject to equitable adjustment following
authorization of the OWNER to the charges.

ARTICLE 10 — TIME

1.
2.

Time limits stated in the Contract Documents are of the essence to the Contract.

If the CONTRACTOR is delayed at any time in progress of the Work by changes ordered
in the Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or
other causes beyond the CONTRACTOR’ control, the Contract Time shall be extended by
Change Order for such reasonable time as may be determined.

ARTICLE 11 —- PAYMENTS AND COMPLETION

1.

The Contract Sum stated in the Agreement, including authorized adjustments, is the total
amount payable by the OWNER to the CONTRACTOR for performance of the Work under
the Contract Documents.