The Contract represents the entire and integrated agreement between the parties and supersedes prior
negotiations, proposals, representations or agreements, either written or oral. Any other documents
which are not listed in this Article are not part of the Contract.
In the event of a conflict between the terms of the Proposals and the terms of this Agreement, a
written change order and/or fully executed OWNER Purchase Order, the terms of this Agreement,
the written change order or the fully executed OWNER Purchase Order shall control over the terms
of the Proposals
ARTICLE 2— WORK TO BE PERFORMED
Except as otherwise provided in this contract, CONTRACTOR shall furnish all services,
equipment, and materials and shall perform all operations necessary and required to carry out and
perform in accordance with the terms and conditions of the contract the work described.
DESCRIPTION OF WORK:
To install nine (9) new vertical gas collection wells with liquid pumping systems, drain tube
surface collection layers, and HDPE geomembrane over the ground surface adjacent to the
residential setback walls in the Phase II landfill to control odors, mitigate fugitive methane
surface emissions and comply with the NHDES approved Operating Plan — Phase I/II/III
Secure Landfill Expansion and the Landfill Gas Collection System Enhanced Monitoring
Protocol/Standard Operating Procedures (EMP/SOP).
ARTICLE 3 — PERIOD OF PERFORMANCE
Project will begin once a written “Notice to Proceed” is issued.
The CONTRACTOR will have 60 calendar days from the date of issuance of the Notice to Proceed
to reach Substantial Completion and 90 calendar days from the date of issuance of the Notice to
Proceed to reach Final Completion.
Substantial Completion is defined as the time at which the Work (or a specified part thereof) has
progressed to the point where, in the opinion of OWNER the Work (or a specified part thereof) is
sufficiently complete, in accordance with the Contract Documents, so that the Work (or a specified
part thereof) can be utilized for the purposes for which it is intended.
Liquated damages of FIVE HUNDRED and 00/100 DOLLARS ($500.00) per_calendar day will
be assessed for delays beyond the established dates for substantial completion and final
completion.
ARTICLE 4— CONTRACT SUM
Subject to additions and deductions by Change Order, the OWNER shall pay CONTRACTOR, in
accordance with the Contract Documents, the Contract Sum of:
FOUR HUNDRED SEVEN THOUSAND EIGHT HUNDRED SIXTY and 00/100 DOLLARS
($ 407,860.00)
The Contract Sum shall include all items and services necessary for the proper execution and
completion of the Work.