ITEM 618.7 - FLAGGERS
A. SCOPE
This work shall consist of furnishing qualified flaggers, as required to direct traffic through or
around the Work as ordered by the Engineer.
B. MATERIALS AND CONSTRUCTION
The Contractor shall supply qualified flaggers as per the latest approved NHDOT Standard
Specifications for Road and Bridge Construction. Daily coverage needs to be approved by the
Engineer.
C. MEASUREMENT AND PAYMENT
Flaggers will be measured by the actual number of hours authorized, as determined by the
Engineer. Payment shall be made at the contract price per hour.
Contractor shall record the number of hours for each flagger used. Hours shall be recorded on a
per street basis. Payment is contingent upon submittal of quantities in a per street format
substantiated with invoices from flagging subcontractor.
Payment will not be made for flaggers who are not equipped with appropriate equipment or who
do not follow standard practice in performing their duties.
Page 35 of 43