CHANGE ORDER
SUMMARY
CHANGE IN CONTRACT PRICE
Original Contract Price:
CHANGE IN CONTRACT TIMES
Original Contract Times:
Substantial Completion:
Ready for Final Payment:
Net Changes from previously approved Change Orders
Net Changes from previously approved Change Orders
Substantial Completion:
Ready for Final Payment:
Contract Price prior to this Change Order:
Contract Times prior to this Change Order:
Substantial Completion:
Ready for Final Payment:
Increase (Decrease) of this Change Order:
Increase (Decrease) of this Change Order:
Substantial Completion:
Ready for Final Payment:
Contract Price with all approved Change Orders:
Contract Times with all approved Change Orders:
Substantial Completion:
° Ready for Final Payment:
RECOMMENDED BY: ACCEPTED BY: ACCEPTED BY:
By: By: By:
Engineer (Authorized Signature) Owner (Authorized Signature) Contractor (Authorized Signature)
Title: Title: Title:
Date: Date: Date:
Change Order # 2 of 2
2021 Paving Program —
Arterial and Collector Roadways