Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 3/17/2021 - P401

Finance Committee - Agenda - 3/17/2021 - P401

By dnadmin on Mon, 11/07/2022 - 13:46
Document Date
Fri, 03/12/2021 - 12:03
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/17/2021 - 00:00
Page Number
401
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__031720…

10.

11.

12.

Recognizing the difficulty in maintaining traffic as well as access to abutting properties,
work on the following streets shall be performed at night: East Hollis Street, Main
Street, and Medical Center Drive.

If traffic and access to abutting properties cannot be maintained during daytime hours on
other streets in the contract to the OWNER’s satisfaction, CONTRACTOR may be
directed to perform the work at night at no additional cost.

Requests for work beyond those hours normally allowed on weekdays shall be made by
the CONTRACTOR at least 72 hours in advance.

Requests for work on Saturdays, Sundays and holidays shall be made at least one week in
advance.

CONTRACTOR should not assume requests for hours beyond the hours and days
normally allowed will be approved. Requests will be considered on a case by case basis.

ADJUSTMENT OF MANHOLES
Manholes shall be adjusted so that finished paving shall be flush with the manhole.

In the instance when manholes are set lower than adjacent pavement by an amount equal
to or greater than 2 inch measured with use of a straight edge, the ENGINEER will at
their sole discretion either require the structure to be readjusted at the CONTRACTOR’s
expense or not make any payment to the CONTRACTOR for the adjustment of the
structure.

In the instance when manholes are set lower than adjacent pavement by an amount less
than % inch measured with use of a straight edge, the ENGINEER may at their sole
discretion either require the structure to be readjusted at the CONTRACTOR’s expense or
not make any payment to the CONTRACTOR for the adjustment of the structure. This
determination will be made with consideration of the location of the manhole with respect
to vehicular, bicycle and pedestrian traffic.

TRACTOR’S REPRESENTATIVE
The CONTRACTOR shall designate a representative who will be available to respond to
emergency calls by the OWNER at any time day and night and on weekends and holidays
should such a situation arise.

Should the City determine action by the City is needed or other costs are incurred because
the CONTRACTOR’s Representative is not available, the City will back-charge the
CONTRACTOR for associated expenses.

HEDULING AND RDINATI
Reference is made to General Conditions Section 2.05, Before Starting Construction and
General Conditions Section 6.04, Progress Schedule.

Prior to the start of construction, the CONTRACTOR shall submit a comprehensive
schedule to the ENGINEER for review and acceptance.

The schedule will identify the number of crews and completion dates for all critical
elements of work.