11.01.A.1 or specifically covered by paragraph 11.01.A.4, all of which are to be considered administrative costs
covered by the CONTRACTOR's fee.
2. Expenses of CONTRACTOR's principal and branch offices other than CONTRACTOR’s office at the Site.
3. Any part of CONTRACTOR's capital expense, including interest on CONTRACTOR's capital employed for the Work
and charges against CONTRACTOR for delinquent payments.
4. Costs due to the negligence of CONTRACTOR, any Subcontractor, or anyone directly or indirectly employed by
any of them or for whose acts any of them may be liable, including but not limited to, the correction of defective
Work, disposal of materials or equioment wrongly supplied, and making good any damage to property.
5. Other overheard or general expense costs of any kind and the costs of any item not specifically and expressly
included in paragraphs 11.01.A and 11.01.B.
C. CONTRACTOR's Fee: When all the Work is performed on the basis of cost-plus, CONTRACTOR's fee shall be
determined as set forth in the Agreement. When the value of any Work covered by a Change Order or when a Claim
for an adjustment in Contract Price is determined on the basis of Cost of the Work, CONTRACTOR’s fee shall be
determined as set forth in paragraph 12.01.C.
D. Documentation: Whenever the cost of the Work for any purpose is to be determined pursuant to paragraphs
11.01.A. and 11.01.B, CONTRACTOR will establish and maintain records thereof in accordance with generally accepted
accounting practices and submit in a form acceptable to ENGINEER as itemized cost breakdown together with
supporting data.
11.02 Cash Allowances
A. It is understood that CONTRACTOR has included in the Contract Price all allowances so named in the Contract
Documents and shall cause the Work so covered to be performed for such sums as may be acceptable to OWNER and
ENGINEER. CONTRACTOR agrees that:
1. The allowances include the cost to CONTRACTOR (less any applicable trade discounts) of materials and
equipment required by the allowances to be delivered at the Site, and all applicable taxes; and
2. CONTRACTOR's costs for unloading and handling on the Site, labor, installation costs, overhead, profit, and other
expenses contemplated for the allowances have been included in the Contract Price and not in the allowances,
and no demand for additional payment on account of any of the foregoing will be valid.
B. Prior to final payment, an appropriate Change Order will be issued as recommended by ENGINEER to reflect actual
amounts due CONTRACTOR on account of Work covered by allowances, and the Contract Price shall be
correspondingly adjusted.
11.03 Unit Price Work
A. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract
Price will be deemed to include for all Unit Price Work an amount equal to the sum of the unit price for each
separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement.
The estimated quantities of items of the Unit Price Work are not guaranteed and are solely for the purpose of
comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and
classifications of Unit Price Work performed by CONTRACTOR will be made by ENGINEER subjects to the provisions of
paragraph 9.08
GC - 41 of 55