neatly recorded as they occur by means of details and notes. No construction work shall be concealed until it has been
inspected, approved, and recorded. The As-built marked prints will be jointly inspected for accuracy and completeness
by the ENGINEER'S representative and a responsible representative of the CONTRACTOR prior to submission of the
monthly pay estimate. Failure to keep the As-built marked prints on a current basis shall be sufficient justification to
suspend pay estimates. The drawings shall show the following information, but not be limited to:
1. The location of any utility lines or other installations of any kind or description known to exist within the
construction area. The location includes dimensions of permanent features.
2. The location and identification of all surface installations within 100 feet of the construction work.
3. The location and dimensions of any changes within the building or structure.
4. Correct grade or alignment of roads, structures, or utilities if any changes were made from Contract Drawings.
5. Correct elevations if changes were made in site grading.
6. Changes in details or design or additional information obtained from working drawings specified to be prepared
or furnished by the CONTRACTOR including but not limited to fabrication, erection, installation plans and placing
details, pipe sizes, insulation material, dimensions or equipment foundations, etc.
7. The topography and grades of all drainage installed or affected as a part of the Work.
8. All changes or modifications which result from the final inspection.
The As-built marked prints shall be delivered to the ENGINEER at the time of final inspection for ENGINEER's review
and approval. All approval and acceptance of As-built drawings shall be accomplished before final payment is made to
the CONTRACTOR.
6.13 Safety and Protection
A. CONTRACTOR shall be solely responsible for initiating, maintaining and supervising all safety precautions and
programs in connection with the Work. CONTRACTOR shall take all necessary precautions for the safety of, and shall
provide the necessary protection to prevent damage, injury or loss to:
1. All persons on the Site or who may be affected by the Work;
2. All the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and
3. Other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways,
structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the
course of construction.
B. CONTRACTOR shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or
to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary
safeguards for such safety and protection. CONTRACTOR shall notify OWNER of adjacent property and of
Underground Facilities and other utility Owner’s when prosecution of the Work may affect them, and shall cooperate
with them in the protection, removal, relocation, and replacement of their property. All damage, injury, or loss to any
property referred to in paragraph 6.13.A.2 or 6.13.A.3 caused, directly or indirectly, in whole or in part, by
CONTRACTOR, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of
them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by
CONTRACTOR (except damage or loss attributable to the fault of Drawings or Specifications or to the acts or omissions