The CONTRACTOR shall plan in advance of forecasted inclement weather events and
shall assign crews to perform maintenance of unpaved areas open to traffic during and
after inclement weather events. CONTRACTOR is responsible to coordinate with the
ENGINEER and other City officials as appropriate.
CONTRACTOR shall be prepared to respond in a timely manner if the City determines
that circumstances warrant action when the CONTRACTOR is not onsite.
DRAINAGE
The CONTRACTOR shall provide necessary measures to provide drainage and minimize
ponding on paved and unpaved surfaces.
The CONTRACTOR shall be responsible to provide means for stormwater runoff to
enter the drainage system at locations where structures are lowered in advance of milling
or reclamation.
During the preconstruction meeting, the CONTRACTOR shall describe provisions to be
made for drainage. Provisions made and methods used shall have been proven by
successful use on past projects of a similar nature.
PROTECTI EFMANHOLE ATCH BASINS AND PIPELINE
Appropriate measures will be taken to protect manholes, catch basins and other structures
as well as pipelines from debris and other materials entering the system through open or
removed covers or grates.
Should material enter the system during the CONTRACTOR’s activities, this material
shall be removed in a timely manner at the CONTRACTOR’s expense.
The CONTRACTOR may be required to clean structures and pipelines downstream of
the location(s) where material entered the system.
The CONTRACTOR may be required to provide closed circuit television (CCTV)
inspection services to verify that material has been removed at the CONTRACTOR’s
expense.
PROTECTI FLANDSCAPI
CONTRACTOR shall take appropriate measures to protect trees, shrubs and other
landscaping. Branches, limbs and roots shall not be cut except with permission of the
ENGINEER.
Where cutting is necessary, work shall be performed by qualified workers.
RESTORATI FEXISTI PROPERTY
The CONTRACTOR shall be responsible for the preservation of all public and private
property and structures, and shall use every precaution necessary to prevent damage
thereto. If damage is done to public or private property, such property shall be promptly
restored by the CONTRACTOR, at his/her expense, to a condition similar or equal to