ADJUSTMENT OF MANHOLES
Manholes shall be adjusted so that finished paving shall be flush with the manhole.
In the instance when manholes are set lower than adjacent pavement by an amount equal
to or greater than 2 inch measured with use of a straight edge, the ENGINEER will at
their sole discretion either require the structure to be readjusted at the CONTRACTOR’s
expense or not make any payment to the CONTRACTOR for the adjustment of the
structure.
In the instance when manholes are set lower than adjacent pavement by an amount less
than % inch measured with use of a straight edge, the ENGINEER may at their sole
discretion either require the structure to be readjusted at the CONTRACTOR’s expense or
not make any payment to the CONTRACTOR for the adjustment of the structure. This
determination will be made with consideration of the location of the manhole with respect
to vehicular, bicycle and pedestrian traffic.
TRACTOR’S REPRESENTATIVE
The CONTRACTOR shall designate a representative who will be available to respond to
emergency calls by the OWNER at any time day and night and on weekends and holidays
should such a situation arise.
Should the City determine action by the City is needed or other costs are incurred because
the CONTRACTOR’s Representative is not available, the City will back-charge the
CONTRACTOR for associated expenses.
HEDULING AND RDINATI
Reference is made to General Conditions Section 2.05, Before Starting Construction and
General Conditions Section 6.04, Progress Schedule.
Prior to the start of construction, the CONTRACTOR shall submit a comprehensive
schedule to the ENGINEER for review and acceptance.
The schedule will identify the number of crews and completion dates for all critical
elements of work.
Detailed updates of the schedule shall be submitted to the ENGINEER for review and
acceptance on at least a monthly interval. Updates shall show work through project
completion.
The OWNER may withhold progress payments if acceptable monthly schedule updates
are not submitted.
The CONTRACTOR shall not increase the number of crews assigned to the work as
identified in the schedule without providing at least one week advanced notice to the
ENGINEER.
SUPERINTENDENCE OF THE WORK
Reference is made to General Conditions Section 6.01, Supervision and Superintendence.
CONTRACTOR shall provide appropriate onsite superintendence of all aspects of the
work whether performed by the CONTRACTOR or by sub-contractors.