1. Each bid submitted to any officer, department, board or commission for the construction of any public
work or improvement must include:
a. The name of each subcontractor who will provide labor or a portion of the work or improvement to
the CONTRACTOR for which he will be paid an amount exceeding 5 percent of the prime
CONTRACTOR’s total bid. Within 2 hours after the completion of the opening of the bids, the general
contractors who submitted the three lowest bids must submit a list of the name of each subcontractor
who will provide labor or a portion of the work or improvement to the CONTRACTOR for which he will
be paid an amount exceeding 1 percent of the prime CONTRACTOR’s total bid or $50,000, whichever is
greater, and the number of the license issued to the subcontractor. If a general CONTRACTOR fails to
submit such a list within the required time, his bid shall be deemed not responsive.
b. A description of the portion of the work or improvement which each subcontractor named in the
bid will complete.
2. The CONTRACTOR shall list in his bid the name of a subcontractor for each portion of the project that
will be completed by a subcontractor.
3. ACONTRACTOR whose bid is accepted shall not substitute any person for a subcontractor who is named
in the bid, unless:
a. The awarding authority objects to the subcontractor, requests in writing a change in the
subcontractor and pays any increase in costs resulting from the change; or
b. The substitution is approved by the awarding authority and:
(i) The subcontractor, after having a reasonable opportunity, fails or refuses to execute a written
contract with the CONTRACTOR which was offered to the subcontractor with the same terms that
all other subcontractors on the project were offered;
(ii) The named subcontractor files for bankruptcy or becomes insolvent; or
(iii) The named subcontractor fails or refuses to perform his subcontract within a reasonable time
or is unable to furnish a performance bond and payment bond.
|. If blasting or use of explosives is necessary for prosecution of Work, the CONTRACTOR shall provide the ENGINEER
with a blasting plan in compliance with OSHA, State, and local regulations, laws, ordinances, and requirements.
CONTRACTOR shall exercise the utmost care not to endanger life or property. CONTRACTOR shall be responsible for all
damage resulting from the use of explosives. CONTRACTOR shall notify each property OWNER and utility company
having structures or facilities in proximity to the site of the work of its intentions to use explosives. Such notice shall be
given sufficiently in advance to enable the utility companies to take such steps as they may deem necessary to protect
their property from injury.
6.10 Taxes
A. CONTRACTOR shall pay all sales, consumer, use, and other similar taxes required to be paid by CONTRACTOR in
accordance with the Laws and Regulations of the place of the Project which are applicable during the performance of
the Work
6.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas
GC - 26 0f 55