  2. Finance Committee - Agenda - 3/17/2021 - P159

Finance Committee - Agenda - 3/17/2021 - P159

By dnadmin on Mon, 11/07/2022 - 13:44
Document Date
Fri, 03/12/2021 - 12:03
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 03/17/2021 - 00:00
Page Number
159
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__031720…

Requirements or Contract Documents to be conducted by or for CONTRACTOR prior to CONTRACTOR’s making
such final commitment; or

c. CONTRACTOR failed to give the written notice within the time and as required by paragraph 4.03.A.

3. If OWNER and CONTRACTOR are unable to agree on entitlement to or on the amount or extent, if any, of any
adjustment in the Contract Price or Contract Times, or both, a Claim may be made therefore as provided in
paragraph 10.05. However, OWNER, ENGINEER, and ENGINEER’s Consultants shall not be liable to CONTRACTOR
for any claims, costs, losses, or damages (including but not limited to all fees and charges of ENGINEERs, architects,
attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by
CONTRACTOR on or in connection with any other project or anticipated project.

4.04 Underground Facilities

A. Shown or Indicated: The information and data shown or indicated in the Contract Documents with respect to
existing Underground Facilities at or contiguous to the Site is based on information and data furnished to OWNER or
ENGINEER by the OWNER’s of such Underground Facilities, including OWNER, or by others. Unless it is otherwise
expressly provided in the Supplementary Conditions:

1. OWNER and ENGINEER shall not be responsible for the accuracy or completeness of any such information or
data; and

2. The cost of all of the following will be included in the Contract Price, and CONTRACTOR shall have full
responsibility for:

a. Reviewing and checking all such information and data,
b. Locating all Underground Facilities shown or indicated in the Contract Documents.

c. Coordination of the Work with the OWNER’s of such Underground Facilities, including OWNER, during
construction, and

d. The safety and protection of all such Underground Facilities and repairing any damage thereto resulting
from the Work.

B. Not Shown or Indicated

1. If an Underground Facility is uncovered or revealed at or contiguous to the Site which was not shown or
indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, CONTRACTOR shall,
promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing
any Work in connection therewith (except in an emergency as required by paragraph 6.16.A). identify the OWNER
of such Underground Facility and give written notice to that OWNER and to OWNER and ENGINEER. ENGINEER will
promptly review the Underground Facility and determine the extent, if any, to which a change is required in the
Contract Documents to reflect and document the consequences of the existence or location of the Underground
Facility. During such time, CONTRACTOR shall be responsible for the safety and protection of such Underground
Facility.

2. If ENGINEER concludes that a change in the Contract Documents is required, a Change Order will be issued to
reflect and document such consequences. An equitable adjustment shall be made in the Contract Price or
Contract Times, or both, to the extent that they are attributable to the existence or location of any Underground
Facility that was not shown or indicated or not shown or indicated with reasonable accuracy in the Contract
Documents and that CONTRACTOR did not know of and could not reasonably have been expected to be aware of

GC-140f55