Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 4/7/2021 - P83

Finance Committee - Agenda - 4/7/2021 - P83

By dnadmin on Mon, 11/07/2022 - 13:44
Document Date
Fri, 04/02/2021 - 12:50
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 04/07/2021 - 00:00
Page Number
83
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__040720…

2021 Sewer Replacement Project - Design, Construction Services & As-built Plans 11Feb21
Paul Engineering Sonsruucton
TASK John Vancor CAD Manager
Hayner Tech :
Denis Hayner
14] $ 175.00 | $ 175.00 | $ 110.00 | $ 110.00 | $ 100.00
Design Services:
2021 Sewer Replacement - Design Plans 8 60 120 120 120
Review 8 16 16 8 16
Total Hours: 16 76 136 128 136
Cost: |$ 2,800.00 |$ 13,300.00 | $ 14,960.00|$ 14,080.00|/$ 13,600.00 $ 58,740.00 |
Construction Services/As-built Plans (16 Weeks):
Full Time Inspection (50 hours/week) 800
Coordination/Req Review/Periodic Visits 16 300
2021 As-built Plans 8 20 80 80
Close Out 8 16 40
Total Hours: 32 336 80 920
Cost: |$ 5,600.00} $ 58,800.00 | $ - $ 8,800.00 | $ 92,000.00 | $ 165,200.00
Reimbursable Expenses:| $ 3,800.00
Total Estimated HSI Fees (Sewer Replacement Project): | $ 227,740.00

2021 Sewer Lining Project - Review of CCTV Video

TASK John Vancor| Paul Hayner | Tom Vancor
$ 175.00 | $ 175.00 | $ 75.00
Video Review & Coordination (12 Weeks):
Review Videos for Linng Contract 380
Coordination 10 60
Total Hours: 10 60 380
Cost:|$ 1,750.00 | $ 10,500.00 | $ 28,500.00 |$ 40,750.00
Total Estimated HSI Fees (Lining Project): |$ 40,750.00

2020 Sewer Replacement Project - As-built Plans

TASK Survey Crew | Paul Hayner CAD Denis Hayner
$ 160.00 | $ 175.00 | $ 110.00 | $ 100.00
As-built Plans Services:
2020 As-Built Plans 24 16 80 80
Cost:|$ 3,840.00|$ 2,800.00/$ 8,800.00 | $ 8,000.00 | $ 23,440.00

Page Image
Finance Committee - Agenda - 4/7/2021 - P83

Footer menu

  • Contact