2020 Sewer Replacement Project As-Built Plans
HSI will prepare As-Built plans for the work performed in the 2020 program.
As detailed in the attached spreadsheets, our proposed budget for this work is $23,440,
Total Not-to-Exceed Budget
2021 Sewer Replacement Program $227,740.00
2021 CIPP Lining Project $ 40,750.00
2020 As-Built Plans $ 23,440.00
Subtotal $291,930.00
Remaining Budget for 2020 Program ($42,436.00)
Total: $249,494.00
We understand that the actual work performed will be as directed and that the task and split of
work between staff may vary. We also understand that actual work performed will be only as
directed and may be less than the budget presented.
If you have any questions or comments regarding this proposal, please contact me.
Sincerely, ,
CKO Dory
John C. Vancor, P.E.
Vice President/Principal Engineer