Summary
CHANGE IN CONTRACT PRICE:
Onginal Contract Price
$48,600.00
Onginal Contract Times
Ready for final payment:
CHANGE IN CONTRACT TIMES:
Substantial completion: Oct 15, 2019
Oct 31, 2019
Net changes from previous Change Orders
$117,200
Net change from previous Change Orders
365 Days
Contract Price prior to this Change Order
$165,800.00
Ready for final payment:
Contract Times prior to this Change Order
Substantial completion: Oct 15, 2020
Oct 31, 2020
Net Increase (deerease} of this Change Order
$100,500.00
Net Increase (decrease) of this Change Order
365 Days
Contract Price with all approved Change Orders
$266,300.00
Ready for final payment:
Contract Times with all approved Change Orders
Substantial completion: Oct 15, 2021
Oct 31, 2021
ACCEPTED:
By
Mayor Jim Donchess
APPROVED:
Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: 03/24/2021 Date: 03/25/21 Date:
Change Order #3 2019 Asphalt Testing 2 of 2