AMENDMENT No. 1
TO
CONTRACT FOR PROFESSIONAL SERVICES
BETWEEN
CITY OF NASHUA
AND
HAYNER/ SWANSON, INC.
This Amendment No.1 made the
ENGINEER).
WHEREAS, an AGREEMENT was entered into on May 7, 2020 between the OWNER and ENGINEER,
day of
2021, by and between The City of
Nashua, New Hampshire (hereinafter called OWNER), and Hayner/Swanson, Inc (hereinafter called
which AGREEMENT is entitled “Pavement Management Engineering Services”.
hereinafter referred to as AGREEMENT.
The AGREEMENT shall be amended to include this Amendment, a copy of which is attached as EXHIBIT A.
CHANGE IN CONTRACT PRICE:
Onginal Contract Price
$398,230.00
CHANGE IN CONTRACT TIMES:
Onginal Contract Times
Contract completion date: December 1, 2020
Net changes from previous Amendments
$0.00
Net change from previous Amendments
0 Days
Contract Price prior to this Amendment
$398,230.00
Contract Times prior to this Amendment
Contract completion date: December 1, 2020
Net Increase (decrease) of this Amendment
$242,500.00
Net Increase (deerease} of this Amendment
395 Days
Contract Price with all approved Change Orders
$640,730.00
Contract Times with all approved Change Orders
Contract completion date: December 31, 2021
Amendment 1 Page 1 of 2
Professional Services
Pavement Management Engineering Services