CHANGE ORDER #4 Paint Assessing Doors $645.15
CHANGE ORDER #4 Assessing Cove Base and tile carpet $1,517.86
CHANGE ORDER #4 Remove Lower Level Double door and frame $2,282.66
CHANGE ORDER #4 Additional Assessing Door Locks $1,611.21
CHANGE ORDER #4 Rotunda Door Add to Project Bid $15,767.35
TOTAL CHANGES #4: $18,951.49
Justification:
Transaction Windows were adjusted from plan to account for additional ADA and customer
interaction.
Additional door hardware was requested or security concerns of changes to doorways.
Credit for HVAC changes not in project — changes to occur to existing system in-house
In agreement with Fire Marshall Lower level doors were removed for better egress.
Rotunda doors were an add-in to the project to comply with CDC social distancing guidelines.
CHANGE ORDER #5 Sprinkler Work in MVR $7,483.74
CHANGE ORDER #5 Door Hardware $3,003.10
CHANGE ORDER #5 Rotunda Door — CREDIT ($2,524.90)
CHANGE ORDER #5 Remove Hand Sanitizers CREDIT ($250.00)
CHANGE ORDER #5 Changes to Roof Top Condenser - CREDIT ($2,011.65)
CHANGE ORDER #5 Furnish Larger DropBox Tax $590.34
CHANGE ORDER #5 Install HVAC Backdraft Dampers $310.85
TOTAL CHANGES: $6,601.48
Justification:
Sprinklers added to the plan per Fire Marshall
Additional door hardware was requested.
Credit for Rotunda Door — lower cost alternative
Credit for Hand Sanitizers — already in house
Credit for Condenser — scope of work reduced
Larger Drop Box required in Tax.
Back draft Dampers for increased HVAC efficiency