City of Nashua, Public Works Division
Board of Public Works Meeting Date: March 25, 2021
David Boucher, Superintendent
Wastewater Department
BCV System Upgrade
To approve the purchase of the Master Control Panel (MCP) upgrade on the Three
Aeration Blowers in the amount of $59,327 from BCV Systems in Springfield, MO.
Funding will be through: Department: 169 Wastewater; Fund: Wastewater; Account
Classification: 81000 Capital Outlay Improvements.
Quote BCV Systems
The Wastewater Department uses three Turblex brand aeration blowers to provide air to
the secondary part of the wastewater facility. The Facility sees process stress during the
summer months where the warmer weather and water make it difficult to maintain
dissolved oxygen levels necessary to support the microbiology of the wastewater system.
We have had BCV System onsite to do service on the Turblex blowers as a sole source
service provider. They have continued to work with us on system optimization of the
blowers. As we continue to work to make the system as efficient as possible, the next step
is to upgrade the MCP program.
BCV is a direct representative of the Turblex brand and is a sole source service provider.