change when the City of Nashua, in its sole discretion, determines that time is critical or public
health and safety are of concern. Any verbal approval shall be confirmed in writing as soon as
practicable. Any change undertaken without prior City of Nashua approval shall not be
compensated and is, at the City of Nashua's election, sufficient reason for contract termination.
CITY OF NASHUA COOPERATION The City of Nashua agrees that its personnel will cooperate
with Service Provider in the performance of its work under this contract and that such personnel
will be available to Service Provider for consultation at reasonable times and after being given
sufficient advance notice that will prevent conflict with their other responsibilities. The City of
Nashua also agrees to provide Service Provider with access to City of Nashua records in a
reasonable time and manner and to schedule items that require action by the Board of Public Works
and Finance Committee in a timely manner. The City of Nashua and Service Provider also agree
to attend all meetings called by the City of Nashua or Service Provider to discuss the work under
the Contract, and that Service Provider may elect to conduct and record such meetings and shall
later distribute prepared minutes of the meeting to the City of Nashua.
DISCOVERY OF CONFLICTS, ERRORS, OMISSIONS, AMBIGUITIES, OR DISCREPANCIES Service
Provider warrants that it has examined all contract documents, has brought all conflicts, errors,
discrepancies, and ambiguities to the attention of the City of Nashua in writing, and has concluded
that the City of Nashua's resolution of each matter is satisfactory to Service Provider. All future
questions Service Provider may have concerning interpretation or clarification of this contract shall
be submitted in writing to the City of Nashua within 10 calendar days of their arising. The writing
shall state clearly and in full detail the basis for Service Provider's question or position. The City
of Nashua representative shall render a decision within 15 calendar days. The City of Nashua's
decision on the matter is final. Any work affected by a conflict, error, omission, or discrepancy
which has been performed by Service Provider prior to having received the City of Nashua's
resolution shall be at Service Provider's risk and expense. At all times, Service Provider shall carry
on the work under this contract and maintain and complete work in accordance with the
requirements of the contract or determination of the City of Nashua. Service Provider is responsible
for requesting clarification or interpretation and is solely liable for any cost or expense arising from
its failure to do so.
TERMINATION OF CONTRACT
A. TERMINATION, ABANDONMENT, OR SUSPENSION AT WILL, The City of Nashua, in its sole
discretion, shall have the right to terminate, abandon, or suspend all or part of the project and
contract at will. If the City of Nashua chooses to terminate, abandon, or suspend all or part of the
project, it shall provide Service Provider 10 day’s written notice of its intent to do so.
If all or part of the project is suspended for more than 90 days, the suspension shall be treated as a
termination at will of all or part of the project and contract.
Upon receipt of notice of termination, abandonment, or suspension at will, Service Provider shall:
1. Immediately discontinue work on the date and to the extent specified in the notice.
Place no further orders or subcontracts for materials, services, or facilities, other than as
may be necessary or required for completion of such portion of work under the contract
that is not terminated.
3. Immediately make every reasonable effort to obtain cancellation upon terms satisfactory
to the City of Nashua of all orders or subcontracts to the extent they relate to the
performance of work terminated, abandoned, or suspended under the notice, assign to
the City of Nashua any orders or subcontracts specified in the notice, and revoke
agreements specified in the notice.
GC 4 of 11