Summary
CHANGE IN CONTRACT PRICE:
Onginal Contract Price
$28,900.00
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: Dec 15, 2019
Ready for final payment: Dec 31,2019
Net changes from previous Change Orders
$30,100.00
Net change from previous Change Orders
366 Days
Contract Price prior to this Change Order
$59,000.00
Contract Times prior to this Change Order
Substantial completion: Dec 15, 2020
Ready for final payment: Dec 31, 2020
Net Increase (deerease} of this Change Order
$31,600.00
Net Increase (decrease) of this Change Order
365 Days
Contract Price with all approved Change Orders
$90,600.00
Contract Times with all approved Change Orders
Substantial completion: Dec 15, 2021
Ready for final payment: Dec 31, 2021
ACCEPTED: APPROVED:
By: By: Wham a By:
William P. Scarpati Mayor Jim Donchess
gineer Owner
(Authorized Signature) (Authorized Signature)
Frederick Moseley, ae
Stantec Consulting Services, Inc.
(Authorized Signature)
Date: 04/29/2021 Date: Date:
Change Order #2 Pavement Management Services 2 of 2