Summary
CHANGE IN CONTRACT PRICE:
Onginal Contract Price
$2,825,135.00
CHANGE IN CONTRACT TIMES:
Onginal Contract Times
Substantial completion: October 30, 2019
Ready for final payment: _November 29, 2019
Net changes from previous Change Orders
$1,824,500
Net change from previous Change Orders
575 days
Contract Price prior to this Change Order
$4,649,635.00
Contract Times prior to this Change Order
Substantial completion: May 30, 2021
Ready for final payment: June 30, 2021
Net Increase (deerease} of this Change Order
$200,000
Net Increase (deerease} of this Change Order
0 days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$4,849,635.00 Substantial completion: May 30, 2021
Ready for final payment: June 30, 2021
RECOMMENDED: ACCEPTED: APPROVED:
VPA SY VV f sa
By; Tay ohn By: /ony. £6, By
DPW ontractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date; O9MAY21 Date: 5/6/2020 Date:
Change Order # 5
IFB01087-021219
2019 CIPP Lining Project 2 of 2