CHANGE ORDER
No. 5
PROJECT: 2019 CIPP Lining Project
OWNER’S CONTRACT NO: IFB1087-021219
EXECUTED CONTRACT DATE: 04/19/19
DATE OF ISSUANCE: 04/29/21 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.:: 148060
CONTRACTOR: Kenyon Pipeline Inspection, LLC
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description:
Kenyon Pipeline Inspection has continued to provide video and pipe lining services to the City into 2021. The
funds in the contract and subsequent change orders have been nearly exhausted but the need for these services
continues to exist. A change order is appropriate until the winner of the 2021 lining and inspection contract can
begin work around June 1, 2021.
A new pay item #13 will need to be established to pay for work previously not identified. Item 13—CCTV
Video Inspection of Catch Basin Laterals Pipe sizes 6” to 12” Including Light Cleaning and Root Cutting will be
paid at $5.00 per linear foot.
Justification:
In order to continue to identify and line ageing sewer pipes, the Division of Public Works Engineering
Department proposes to extend Kenyon’s existing 2019 CIPP Lining Contract further into 2021 by awarding a
$200,000 Change Order. This is a stop-gap change order until Green Mountain Pipeline Services can begin work
on their 2021 contract around June 1, 2021.
Change Order # 5
IFB01087-021219
2019 CIPP Lining Project 1 of 2