Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 5/19/2021 - P180

Finance Committee - Agenda - 5/19/2021 - P180

By dnadmin on Mon, 11/07/2022 - 13:41
Document Date
Fri, 05/14/2021 - 13:59
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 05/19/2021 - 00:00
Page Number
180
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__051920…

To:

From:

Re:

E. Motion:

Discussion:

City of Nashua, Public Works Division

Board of Public Works Meeting Date: April 29, 2021

Daniel Hudson, P.E., City Engineer
Engineering Department

2019 CIPP Lining Project
Change Order No. 5

To approve Change Order No. 5 for the 2019 CIPP Lining Project with Kenyon Pipeline
Inspection of Queensbury, NY in the amount of $200,000. Funding will be through
Department: 169 Wastewater; Fund: Wastewater; Activity: Stormwater Abatement.

Kenyon Pipeline Inspection was the low bidder of the 2019 CIPP Lining Project and has
performed well over the course of the contract completing CCTV inspection and lining
of both sewer and drain pipes. Four previous change orders have been approved to extend
their services.

The Engineering Department would like to continue to use the services of Kenyon to
identify pipes that need rehabilitation until the contractor for the 2021 CIPP Lining
contract can begin work in early June. CCTV inspection of sewers in roads proposed to
be paved in the Paving Program would be included in this work. Deteriorated sewers may
also be lined under this change order, as needed.

With this change order, the amended contract value will be $4,849,635.