with their other responsibilities. The City of Nashua also agrees to provide Professional
Engineer with access to City of Nashua records in a reasonable time and manner and to
schedule items that require action by the Board of Public Works and Finance Committee
in atimely manner. The City of Nashua and Professional Engineer also agree to attend all
meetings called by the City of Nashua or Professional Engineer to discuss the work under
the Contract, and that Professional Engineer may elect to conduct and record such meetings
and shall later distribute prepared minutes of the meeting to the City of Nashua.
DISCOVERY OF CONFLICTS, ERRORS, OMISSIONS, AMBIGUITIES, OR DISCREPANCIES
Professional Engineer warrants that it has examined all contract documents, has brought
all conflicts, errors, discrepancies, and ambiguities to the attention of the City of Nashua
in writing, and has concluded that the City of Nashua's resolution of each matter is
satisfactory to Professional Engineer. All future questions Professional Engineer may have
concerning interpretation or clarification of this contract shall be submitted in writing to
the City of Nashua within 10 calendar days of their arising. The writing shall state clearly
and in full detail the basis for Professional Engineer's question or position. The City of
Nashua representative shall render a decision within 15 calendar days. The City of Nashua's
decision on the matter is final. Any work affected by a conflict, error, omission, or
discrepancy which has been performed by Professional Engineer prior to having received
the City of Nashua's resolution shall be at Professional Engineer's risk and expense. At all
times, Professional Engineer shall carry on the work under this contract and maintain and
complete work in accordance with the requirements of the contract or determination of the
City of Nashua. Professional Engineer is responsible for requesting clarification or
interpretation and is solely liable for any cost or expense arising from its failure to do so.
TERMINATION OF CONTRACT
A. TERMINATION, ABANDONMENT, OR SUSPENSION AT WILL. The City of Nashua, in its
sole discretion, shall have the right to terminate, abandon, or suspend all or part of the
project and contract at will. If the City of Nashua chooses to terminate, abandon, or
suspend all or part of the project, it shall provide Professional Engineer 10 day’s written
notice of its intent to do so.
If all or part of the project is suspended for more than 90 days, the suspension shall be
treated as a termination at will of all or part of the project and contract.
Upon receipt of notice of termination, abandonment, or suspension at will, Professional
Engineer shall:
1. Immediately discontinue work on the date and to the extent specified in the notice.
Place no further orders or subcontracts for materials, services, or facilities, other
than as may be necessary or required for completion of such portion of work
under the contract that is not terminated.
3. Immediately make every reasonable effort to obtain cancellation upon terms
satisfactory to the City of Nashua of all orders or subcontracts to the extent they
relate to the performance of work terminated, abandoned, or suspended under the
notice, assign to the City of Nashua any orders or subcontracts specified in the
notice, and revoke agreements specified in the notice.
4. Not resume work after the effective date of a notice of suspension until receipt of
a written notice from the City of Nashua to resume performance.
GC 4 of 13