NASHUA TRANSIT CENTER CONSTRUCTION PHASE SERVICES
SCOPE OF WORK
The Engineer has prepared this Contract Agreement for services related to construction of the Nashua
Transit Center Retrofit Project. This Scope of Work includes only Construction Services, with all
previously contracted work being complete at this time, including Initial Project Scoping, Engineering /
Feasibility Study / Preliminary Plans, Final Plans, and Bidding Services.
The following Scope of Work has been established for Construction Services to be performed by the
Engineer, based on discussions with the City, to date.
CONSTRUCTION SERVICES
The following Scope of Work is anticipated to be required by the Engineer during construction of the
Nashua Transit Center Retrofit Project. All work described below represents services and level-of-effort
anticipated to be required on this project, based on our understanding of the City’s expectations and
our experience on similar projects. Furthermore, for estimating purposes, the Engineer has assumed
that construction will be completed over a 17-week or 120-day period.
Construction Administration
The Engineer will provide construction administration services relative to the retrofit improvements. This
work is anticipated to include the following:
e Conduct a pre-construction meeting with the City of Nashua, project stakeholders, impacted
utility owners, and the contractors;
e Review and approval of shop drawings;
e Consultation with the City and project stakeholders;
e Respond to Requests for Information (RFI) and Change Orders from the Contractor;
e Participation at weekly construction progress meetings (when requested);
e Consultation and advice during construction;
e Attendance at a final inspection;
e Preparation of a punch list upon substantial completion;
e §=6Certification that all work is completed in accordance with the Contract Documents; and
e Conduct Project Close Out, including final pay estimate and compilation of record documents.
The following level-of-effort is anticipated by the Engineer, based on a 17-week construction schedule:
Task Hours/Week Weeks Total Hours
Pre-Construction Conference 6 1 6
Shop Drawing Review 10 4 40
Meetings/Change Orders 2 17 34
Field Consultation 2 17 34
Punch List, Final Inspection & Certification 8 2 16
Project Close Out 25 2 50
Total: 180