Item No. 1 - Newton Conduit Extension
EXTRA WORK ORDER RECAP SHEET
Project : Nashua WWTP Pump Station Upgrades
Change in Service Location- Newton Pump Station
1) LABOR COST $668.72
2.) DIRECT LABOR COSTS $220.68
3.) MATERIAL COST $0.00
4) EQUIPMENT COST $1,396.00
5.) OVERHEAD/PROFIT 15 % OF (1) + (2) + (3) + (4) $342.81
6.) SUBTOTAL $2,628.21
7.) SUBCONTRACTOR'S WORK VALUE $0.00
8.) SUBCONTRACTOR 10% M/U $0.00
8.) TOTAL $2,628.21
TOTAL Cost = $2,628.21
This is the cost to extend the electrical service trench for Newton Station