Document Date
Meeting Description
Document Type
Meeting Date
Page Number
30
Item No. 1 - Newton Conduit Extension
EXTRA WORK ORDER RECAP SHEET
Project : Nashua WWTP Pump Station Upgrades
Change in Service Location- Newton Pump Station
1) LABOR COST $1,294.04
2.) DIRECT LABOR COSTS $427.03
3.) MATERIAL COST $0.00
4) EQUIPMENT COST $1,396.00
5.) OVERHEAD/PROFIT 15 % OF (1) + (2) + (3) + (4) $467.56
6.) SUBTOTAL $3,584.63
7.) SUBCONTRACTOR'S WORK VALUE $0.00
8.) SUBCONTRACTOR 10% M/U $0.00
8.) TOTAL $3,584.63
TOTAL Cost = $3,584.63
This is the cost to extend the electrical service trench for Newton Station
Page Image