Item No. 1 - Newton Conduit Extension
Change in Service Location- Newton Pump Station
Date: 12-Mar-20
Description: Change in Service Location- Newton Pump Station
Duration : 1 Shif/Shifts
A: LABOR #men Hours Rate/Hour Shifts Total
Foreman-Jim 1 2.5 $ 70.82 1 $ 177.05
O/T 1 $ 106.23 1 $ -
Operator 1-Norman 1 2.5 $ 53.73 1 $ 134.33
O/T $ 80.60 1 $ -
Lab 3-Brandon 1 2.5 $ 57.54 1 $ 143.85
O/T $ 86.31 1 $ -
Truck Drv-Tom 1 2.5 $ 54.02 1 $ 135.05
O/T $ 81.03 1 $ -
Lab 1- Barry 1 2.5 $ 57.54 1 $ 143.85
O/T $ 86.31 1 $ -
Lab 2- Pablo 1 2.5 $ 57.54 1 $ 143.85
O/T $ 86.31 1 $ -
Labor subtotal:[$ ____ 877.98]
B: LABOR BENEFITS #men Hours Rate/Hour Shifts
Foreman-Jim 1 2.5 $ - 1 $ -
Operator 1-Norman 1 2.5 $ 29.86 1 $ 74.65
Lab 3-Brandon 1 2.5 $ 28.76 1 $ 71.90
Truck Drv-Tom 1 2.5 $ - 1 $ -
Lab 1- Barry 1 2.5 $ - 1 $ -
Lab 2- Pablo 1 2.5 $ - 1 $ -
Subtotal Fringes[$______—_—-146.55]
Cc: Material Qty. Unit Unit Cost
Concrete 25 cY $ 145.00 $ 3,625.00
$ -
$ -
$ -
$ -
Subtotal Material:
D: EQUIPMENT Qty Hours Rate/Hour Shifts
Cat 345 Exc 1 $105.00 1 $ -
Cat 950 Loader 1 $65.00 1 $ -
Skid Steer 1 0 $72.00 1 $ -
Yanmar 100 1 2.5 $72.00 1 $ 180.00
4300 Gradall 1 $68.00 1 $ -
Generator 50KW 1 $15.00 1 $ -
Tri Axle 1 2.5 $90.00 1 $ 225.00
Trailer-Lowbed 1 $125.00 1 $ -
Trailer-Dump 1 $125.00 1 $ -
Crew Truck 1 2.5 $12.50 1 $ 31.25
Concrete Pump Truck 1 1 $975.00 1 $ 975.00
Subtotal Equipment [$___1,414.25 |
E: SUBCONTRACTORS Qty. Unit Unit Cost
PARA A LF
Subcontractor Total[s id