28
Item No. 1 - Newton Conduit Extension
EXTRA WORK ORDER RECAP SHEET
Project : Nashua WWTP Pump Station Upgrades
Change in Service Location- Newton Pump Station
1) LABOR COST $1,024.53
2.) DIRECT LABOR COSTS $338.09
3.) MATERIAL COST $3,625.00
4) EQUIPMENT COST $1,411.25
5.) OVERHEAD/PROFIT 15 % OF (1) + (2) + (3) + (4) $959.83
6.) SUBTOTAL $7,358.70
7.) SUBCONTRACTOR'S WORK VALUE $0.00
8.) SUBCONTRACTOR 10% M/U $0.00
8.) TOTAL $7,358.70
TOTAL Cost = $7,358.70
This is the cost to extend the electrical service trench for Newton Station
Page Image