Item No. 1 - Newton Conduit Extension
Change in Service Location- Newton Pump Station
Date: 11-Mar-20
Description: Change in Service Location- Newton Pump Station
Duration : 1 Shif/Shifts
A: LABOR #men Hours Rate/Hour Shifts Total
Foreman-Jim 1 2 $ 70.82 1 $ 141.64
O/T 1 $ 106.23 1 $ -
Operator 1-Norman 1 2 $ 53.73 1 $ 107.46
O/T $ 80.60 1 $ -
Lab 3-Brandon 1 0 $ 57.54 1 $ -
O/T $ 86.31 1 $ -
Truck Drv-Tom 1 2 $ 54.02 1 $ 108.04
O/T $ 81.03 1 $ -
Lab 1- Barry 1 2 $ 57.54 1 $ 115.08
O/T $ 86.31 1 $ -
Lab 2- Pablo 1 2 $ 57.54 1 $ 115.08
O/T $ 86.31 1 $ -
Labor subtotal:[$_____ 587.30]
B: LABOR BENEFITS #men Hours Rate/Hour Shifts
Foreman-Jim 1 2 $ - 1 $ -
Operator 1-Norman 1 2 $ 29.86 1 $ 59.72
Lab 3-Brandon 1 0 $ 28.76 1 $ -
Truck Drv-Tom 1 0 $ - 1 $ -
Lab 1- Barry 1 0 $ - 1 $ -
Lab 2- Pablo 1 2 $ - 1 $ :
Subtotal Fringes[$______—_—_—=8 9.72]
Cc: Material Qty. Unit Unit Cost
$ -
$ -
$ -
$ -
$ -
Subtotal Material:
D: EQUIPMENT Qty Hours Rate/Hour Shifts
Cat 345 Exc 1 $105.00 1 $ -
Cat 950 Loader 1 $65.00 1 $ -
Skid Steer 1 0 $72.00 1 $ -
Yanmar 100 1 2 $72.00 1 $ 144.00
4300 Gradall 1 $68.00 1 $ -
Generator 50KW 1 $15.00 1 $ -
Tri Axle 1 2 $90.00 1 $ 180.00
Trailer-Lowbed 1 $125.00 1 $ -
Trailer-Dump 1 $125.00 1 $ -
Crew Truck 1 2 $12.50 1 $ 25.00
Concrete Pump Truck 1 0 $975.00 1 $ -
Subtotal Equipment [$___349.00]
E: SUBCONTRACTORS Qty. Unit Unit Cost
$ -
$ -
$ -
$ -
$ -
Subcontractor Total[s id