Item No. 1 - Newton Conduit Extension
EXTRA WORK ORDER RECAP SHEET
Project : Nashua WWTP Pump Station Upgrades
Change in Service Location- Newton Pump Station
1) LABOR COST $2,588.08
2.) DIRECT LABOR COSTS $854.07
3.) MATERIAL COST $0.00
4) EQUIPMENT COST $1,396.00
5.) OVERHEAD/PROFIT 15 % OF (1) + (2) + (3) + (4) $725.72
6.) SUBTOTAL $5,563.87
7.) SUBCONTRACTOR'S WORK VALUE $0.00
8.) SUBCONTRACTOR 10% M/U $0.00
8.) TOTAL $5,563.87
TOTAL Cost = $5,563.87
This is the cost to extend the electrical service trench for Newton Station
Page Image