Document Date
Meeting Description
Document Type
Meeting Date
Page Number
22
Item No. 1 - Newton Conduit Extension
EXTRA WORK ORDER RECAP SHEET
Project : Nashua WWTP Pump Station Upgrades
Change in Service Location- Newton Pump Station
1) LABOR COST $970.53
2.) DIRECT LABOR COSTS $320.27
3.) MATERIAL COST $0.00
4) EQUIPMENT COST $523.50
5.) OVERHEAD/PROFIT 15 % OF (1) + (2) + (3) + (4) $272.15
6.) SUBTOTAL $2,086.45
7.) SUBCONTRACTOR'S WORK VALUE $0.00
8.) SUBCONTRACTOR 10% M/U $0.00
8.) TOTAL $2,086.45
TOTAL Cost = $2,086.45
This is the cost to extend the electrical service trench for Newton Station
Page Image