Memo: Nashua Pump Station — Phase 1 Change Order No. 2
4/20/2021
Page 3 of 3
control panel §
| Hocation
iil)
os
e
5
4)
2
[>
(3)
Item No. 2 Balancing Change Order Item — ($100.00)
Bid Item No. 9 — Misc. Concrete, was given a unit price on Defelice’s bid of $1.00/cubic yard for
an estimated 100 cubic yards. This will result in a reduction of the contract price by $100.00.
Time Extension — 36 days
A time extension was granted to Defelice of 36 days for Final Completion. The work to be
completed includes the replacement of the frames and covers at Gillis Street and the completion
of the Punchlist items. The new date for Final Completion is 5/21/2021.
Substantial Final
Milestone Completion Completion
Original Contract Dates 8/14/2020 9/13/2020
Time Extension (Result of Change Order 1) 70 days 214 days
Time Extension (Result of Change Order 2) 0 days 36 days
New Contract Dates 10/23/2020 5/21/2021